Name of Project: 200t/h CDQ system project for the environmental protection relocation project of Qingdao Iron and Steel Co., Ltd.
Service: EPC
Capacity: 1×200t/h
Type of Coke Oven: 7m top-charging coke oven
Start of Construction: February 2014
Month of Startup: April 2016